Project is located in Platte City, MO.
The project consists of the construction of wastewater pump station and force main to provide service to the new Windmill Creek Subdivision east of I-29 and south of Hwy 92.
Project Engineer: Shafer, Kline & Warren, Inc.
Contractor: M CON, LLC
Project Superintendent: AJ Jensen
Project Foreman: Kenny Klaus
The sewer system will include furnishing and installing:
Site grading, fencing and granular access road.
10’x10’ precast wetwell, valve vault, flow meter vault, and jib crane, trolley
hoist and piping.
Concrete pads for electric panel, transformer pad, and generator and concrete base for SCADA antenna.
2,972 LF of 6” PVC force main, 840 LF of 6”PVC HDPE horizontal directional drilling and 342 LF of 6” HDPE carrier pipe in 18” casing pipe.
68 LF of 18” gravity sewer and one 5’ diameter manhole.
Electrical panels, breakers, meter, automatic transfer switch, conduit and wiring.
The system shall also include installation of the following owner furnished equipment:
Two 435 gpm submersible pumps and guide rails, elbows, brackets and lifting assembly.
Pump Control Panel including SDADA panel and AFD’s.
SCADA antenna.
Wetwell aeration unit and blower.